Z1DA--NRM CONSTRUCTION -528A8-18-801 Renovate for Cardiac Cath & IR

VETERANS AFFAIRS, DEPARTMENT OF

About this opportunity

This amendment answers the following vendor questions: Is lead lining required for the concrete floor in the space? Specifications call for installation of floor lead. See Physicists report Please advise. Answer: The installation of lead lining is not necessary as the existing concrete is thick enough.� If flooring concrete/topcoat removal is required during construction, the contractor shall return the impacted area back to its original specifications. Who is responsible to remove the office furniture that is currently in the construction space? Answer: The VA shall be responsible for the removal of office furniture and other misc. items stored in the construction area. For the above ceiling structural steel install in the 1st floor lobby: Who will be responsible to rework the existing du...