P400--Building 149 and 150 Demolition 552-26-201
VETERANS AFFAIRS, DEPARTMENT OF
About this opportunity
Question: Page 9 of 74 solicitation reference Additional Considerations for Building 150 Par F.. Provide a detailed description of all hazardous materials located in the structure and provide it to the COR Is testing required to identify all hazardous materials, and who is responsible for identifying any/all of the materials that will require testing to be designated (or not) as hazardous? Answer: Due to the extent of the structural failure, all materials shall be considered to be hazardous. The identification of the materials shall account for the type. The VA needs to account for what hazardous materials are located in the demo site for disposal. Question: Page 5 of 74 solicitation reference Utility Removal and Termination Par(s) A, B, C, D Removal and safe termination of (steam, condens...