J041--Chiller 7 & Pumps Replacement RFQ

VETERANS AFFAIRS, DEPARTMENT OF

About this opportunity

Contractor Questions and Government Answers Government Answers provided to the best of our knowledge, Contractor is responsible for field verification of all existing conditions to confirm accuracy.� A site visit is highly recommended. Is this a brand-new contract OR is (was) there an incumbent performing these services? This is a new, stand alone requirement for the replacement of Chiller #7. If not brand-new, can you please provide the current/previous contract number? N/A as this is a brand new contract. The following questions (4-15) are for some clarification on the SOW: Provide new Chiller: York Chiller Air Cooled Screw Chiller - Model: YVAA0213. Is this a Sole Source requirement� or are or equal chillers acceptable? LIKE FOR LIKE What is the specific tonnage required for the chiller...