TSS Ductless System at EWR ATCT - Amendment 03
TRANSPORTATION, DEPARTMENT OF
Who can apply
Total Small Business Set-Aside (FAR 19.5). SBA
About this opportunity
Amendment 03 - Extend Q&A due date to 04/14/26 at 1800 CT Amendment 02 - Provide updated documents for Section J Amendment 01 - Provide site visit information Mechanical � Install (3) indoor wall-mounted units, along with all refrigerant and drain piping. � Install (1) 6-ton heat pump. Unit to be anchored to exterior concrete wall via on L-bracket steel frame. � Coordinate core penetrations through concrete wall for piping, electrical, and drain lines. Installation to include all wall waterproofing. � Provide and insulate all refrigerants and condensate piping above ceiling � Test and charge system to verify operation. Electrical � Install new dedicated 208V, 3-phase power circuit � Provide NEMA 4X, 60A non-fused stainless steel disconnect at outdoor unit � Provide power and control condui...