Custer Gallatin NF - Fairy Lake Phase 2 Road & Recreation Improvements

AGRICULTURE, DEPARTMENT OF

Who can apply

Total Small Business Set-Aside (FAR 19.5). SBA

About this opportunity

4/14/26- Amendmenr 0001 will bew issued on 4/15 to gove updated easy access Attachment 2 Schedule of Items. Time extension of 1 week will be granted. Stay tuned for 4/15 Amendment 0001. 4/9/26 - Q&A Posted Fairy Lake Phase 2 Road and Recreation Improvements on the Bozeman RD of the Custer Gallatin National Forest. This project will include excavation, drainage, road reconditioning, surface stabilization, trail reconditioning and surfacing, and installation of new turnouts, vault toilet(s), aggregate and 2 AOP culverts. Work will be performed in accordance with FP-24, Forest Service Supplemental Specifications and project specific requirements. The work anticipated under any contract resulting from the solicitation will be started following Phase 1 which is currently anticipated to be compl...