H312--Fire System Inspection & Testing
VETERANS AFFAIRS, DEPARTMENT OF
About this opportunity
RESPONSE: Per NFPA 25 13.4.5.2.2.2 a full trip test of dry systems is required every three years, and an air leakage test of dry systems every three years per NFPA 13.4.5.2.9.� for the following buildings.� Years for testing shall be Base Year FY26, and Option Year 3 FY29. Building 14 Building 22/69 Building 49 Building 60 Building 128 Building 129 Building 130 Building 131 (This is in SOW, written this way, for the full dry trip test).� (This is not in the SOW but NFPA 25 states)- 13.4.3.2.3- During the years when full flow testing in accordance with 13,4,4,2,2 is not required, the Preaction valve shall be trip tested with the control valve partially open. As far as the quarterly, semi-annual, annual testing it would make no sense to do a quarterly test, then right after doing a semi-annu...