Procurement of Various Spares for the MH-65E Aircraft
HOMELAND SECURITY, DEPARTMENT OF
Who can apply
Total Small Business Set-Aside (FAR 19.5). SBA
About this opportunity
Amendment One is to answer the following questions: QUESTION 1: Do we have to fulfill or complete all items or nothing? ANSWER: All line items are not required to be quoted to be considered. QUESTION 2: Do we need to bid for all options, or can we bid on the base only? ANSWER: If the base period is the only option quoted, the quote will be found not technically acceptable due to being unable to fulfill the requirement of base plus four option periods. QUESTION 3: What do you mean by "Manf. Code" in Excel column? ANSWER: The �Manf. Code� column refers to the Original Equipment Manufacturer (OEM) that you are quoting for the part. ___________________________________________________________________________________________________ This is a combined synopsis/solicitation for commercial items p...