Z--Cableway Crane Refurbishment
INTERIOR, DEPARTMENT OF THE
About this opportunity
The Bureau of Reclamation, Interior Region 8: Lower Colorado Basin (LCB) is issuing a Request for Proposal (RFP) for a firm fixed-price contract for the 150-ton cableway crane at the Hoover Dam that needs to be refurbished. The Bureau of Reclamation, Interior Region 8: Lower Colorado Basin has a requirement for the 150-ton cableway crane at the Hoover Dam that needs to be refurbished. The ground to the middle of the track cables is approximately 600 feet. When work is being completed on the NV tower, the ground is approximately 100 feet below. The track cables spans from the AZ anchorage to behind the NV tower. The length of the track cable is 1,615�, most of which is above the canyon. The principal components of work include: 1. Replace the 6, 3-�" track cables. 2. Replace the 2, 1-1/8" b...