DESC2103C - Bulk Fuel Storage Tanks Phase II, Yokota Air Base, Japan
Record: https://fundinglandscape.com/opportunity/cmtv567p800nxjt04jn13jruu · Official notice: https://sam.gov/workspace/contract/opp/722fdc916e5744dfb0d68fdd3d992fd3/view
Open. Deadline Jan 25, 2027 at 2:00 PM UTC+9. Notice W912HV26RA009. (current status: https://fundinglandscape.com/opportunity/cmtv567p800nxjt04jn13jruu)
Deadline: Jan 25, 2027 at 2:00 PM UTC+9. Add to calendar: https://fundinglandscape.com/opportunity/cmtv567p800nxjt04jn13jruu/deadline.ics (Google Calendar: https://fundinglandscape.com/opportunity/cmtv567p800nxjt04jn13jruu/calendar/google)
Issuer: DEPT OF DEFENSE
Submit through the official notice: https://sam.gov/workspace/contract/opp/722fdc916e5744dfb0d68fdd3d992fd3/view
Funding Landscape's record of a notice published on SAM.gov.
Update 10 September 2026: Attached Pre-Proposal Conference Slides.
- Status
- Open
- Due
- Jan 25, 2027, 2:00 PM UTC+965 days left
- Issuer
- Department of Defense
- Notice number
- W912HV26RA009
Funding Landscape alerts
Email me listings like thisClose email options
Email me listings like this
Department of Defense
You'll get new contracts from Department of the Army.
Weekly emails when there are new matches. You may also receive an initial email. Stop any time.
Description
Read the full description
Project Title: DESC2103C - Bulk Fuel Storage Tanks Phase II. Project Description: Construct one 100,000-barrel cut-and-cover JP-8 storage tank. A pump house is to be provided on the top of the tank and contain four 600-gpm issue vertical turbine pumps and one 50-gpm water draw off vertical turbine pump. The new tank will include a high-level valve, independent level alarms, and the hardware necessary for the automatic tank gauging (ATG) system. The new tank includes piping, valves, vaults and appurtenances connecting to an existing filter separator building.
The new control system of the new tank will be connected to the existing filter building that houses pump control Programmable Logic Controller (PLC) and Human Machine Interface (HMI), automatic tank gauge (ATG) reporting module capable of reporting inputs from all Eastside Fuel Facility tanks. A product saver tank is to be provided for the new bulk storage tank. The Pump House will be of reinforced concrete construction and site adapted to meet local conditions. The roof will be a low slope concrete roof with built-up roofing with overhangs over doorways. The tank is to be steel with concrete outer wall with a rolling cover for access to tank mounted equipment.
The product recovery pump will return reclaimed fuel back through receipt filtration to the bulk storage tanks.
About Funding Landscape
Open grants and government contracts.
Search open grants and contracts on Funding Landscape
Find similar listings
See more open contract opportunities like this
Funding Landscape alerts
Get new bids for the work you do
Choose your keywords and state, then confirm a weekly email alert.
Choose my bid alert