P--WICR Demolition and Removal of Excess Building Etc

INTERIOR, DEPARTMENT OF THE

About this opportunity

Demolition and Removal of Excess Building, Wilson's Creek National Battlefield (WICR) The purpose of this amendment is to provide the site visit roster and answers to the questions asked thus far. Q1. Can the deliver by date be negotiated with the contractor? or is this a strict date for completion? A1. 180 Days After Award is required. Q2. Does this project require any bonds? for example bid bond? Payment and performance bonds? A2. This work is being done as a service, not construction. Bonds are not expected to be necessary for this work; therefore, none are required. Q3. Could you please confirm the depth of the existing well at the site? A3. Depth of well is unknown, Missouri DNR did not start keeping records until 1987. For questions, contact: James Bissaillon Contract Specialist jame...