Z2NZ--631-19-002 Upgrade Steam Distribution System Phase II Industry Day Recap

VETERANS AFFAIRS, DEPARTMENT OF

About this opportunity

631-19-002 Upgrade Steam Distribution System Phase 2 Industry Day Recap Understand Challenges for construction regarding this project from a contractor s perspective. Is there any ability to alter phasing? VA Response: In-short, yes. As a result of your inquiries the project team is proposing phasing to turn over both basement and first floor wings coordinate well in advance to close, relocate, or adjust clinical operations for a fixed period. This includes a lengthy shut down of the canteen in summer months. This will allow more day shift work, more sustained/efficient construction avoiding nightly restoration. With careful planning and temporary heat provision plans by contractor this could also permit work during heating season. The solicitation will contain an updated phasing supplemen...