Work includes:⢠N Henry Street: Install by jack and bore 192 linear feet of 12-inch SDR 26 PVC sanitary sewer pipe with steel casing pipe. ⢠Vernon Street: Replace 351 linear feet of 12inch RCP sanitary sewer pipe with 351 feet of 12-inch SDR 26 PVC sanitary sewer pipe. ⢠Disconnect sanitary sewer system from the combined sewer at intersection of Colonial Avenue and Vernon Street. ⢠Connect two existing manholes with new sanitary sewer. ⢠Install two new sanitary manholes with different sizes. See the project page in Euna:https://alexandriava.bonfirehub.com/opportunities/223887