HUM MALSR Demo and Replacement
TRANSPORTATION, DEPARTMENT OF
About this opportunity
Amendment 0003 posted on 29 June 2026 See formal SF30 Amendment titled "6973GH-26-R-00111 Amendment 0003" in the attachments/links section. This amendment makes changes to the solicitation as detailed on page 1 of the amendment which states: The purpose of this Amendment 0003 is to do the following: 1. Extend the close date of the proposal from 10 July 2026 to 24 July 2026 2. Correct Period of Performance to 365 days after Notice to Proceed has been issued. Construction will be completed in phases. 3. In Section B, add an additional pricing line for Access Road alternatives (concrete vs asphalt) 4. Incorporate the following attachments: - 25-504452.1_Pre-Demolition_Asbestos_and_Lead-Based_Paint_Survey_-_FAA,_Houma,_LA_090425 - HUM MALSR FUGRO GEOTECHNICAL REPORT - HUM_MALSR_AS-BUILTS 1 5. ...