USCGC MUNRO GAS TURBINE BLEED AIR HOSE INSULATION
HOMELAND SECURITY, DEPARTMENT OF.US COAST GUARD.SFLC PROCUREMENT BRANCH 2(00085)
Who can apply
8(a) Set-Aside (FAR 19.8)
About this opportunity
Mofification 1 to this solicitation was to correct the POP in the attached SOW. Correct: period of performance for this contract shall be between 01JUL2026 & 15JUL26. STATEMENT OF WORK (SOW) FOR GAS TURBINE BLEED AIR HOSE INSULATION CGC MUNRO has a need to replace insulation covers on the Gas Turbine Bleed Air Hose. The ship’s Main Gas Turbine is currently non-operational and has an immediate need for new insulation materials as outlined in this Statement of Work (SOW). 1.0 GENERAL Background USCGC MUNRO inadvertently soaked the insulation surrounding GTBA-HOSE-1 with an oily water. The hose is for the anti-icing bleed air system located underneath the Main Gas Turbine Module. Inundated insulation causes smoking when the Gas Turbine is operated in external temperatures above 40 degrees; pr...