IFB Improve Campus Utilities Infrastructure - Electrical

Radford University

View solicitation at Radford University

Free. Verify your email, then we send one reminder only.

Posted
Jul 28, 2026
Closes
Sep 1, 2026 (in 35 days)

About this opportunity

Installation of a 13‑section lineup of 4.16 kV main‑tie‑main switchgear, positioned within an outdoor protected‑aisle enclosure and installed on a cable vault. The includes construction of underground ductbanks and installation of cables to provide feeders from the RED substation, a feeder tie-in to the CHP, associated distribution feeders, and reconfigure feeders to support construction phasing. The project also includes modifications to the RED substation to support the upgraded electrical infrastructure.